    Trailblazer got a reaction from dooright in Trail 3 complete   
    With the news of the Pessimite agreement and now the completion of several bridges on the North Shore Sept Isles, Havre St. Pierre and Baie Johan Beetz is now at our grasp.
    Below is the translation of the arcticle
    🎉 NEW ACHIEVEMENTS 🎉
    In the heart of Minganie, one of the largest snowmobile footbridge construction projects in the country is ending, namely the construction of 5 footbridges, 4 of which will serve the FCMQ trail. For almost 2 years, winter and summer, our team has been building footbridges on the Tortue, Aisley, Romaine rivers as well as Lac Cormier.
    We would first like to thank the SEIE, Les Constructions Mackenzie as well as the Innu Council of Ekuanitshit of Longue-Pointe-de-Mingan for their trust in our organization. Thank you also to all our subcontractors who participated directly or indirectly in the realization of these projects. Without forgetting, a huge thank you to all our valuable employees who brought these major projects to fruition! 💪
    Footbridge over the Tortue River
    23 ml long. and with a capacity of 20 t.m, this footbridge should allow the resumption of maintenance of the trail east of Sept-Îles which had been ungroomed for several years due to this missing bridge towards Havre-St-Pierre.
    Cormier Lake Footbridge
    235' long and with a capacity of 10 t.m, this footbridge is located above the Romaine 1 reservoir at km 19 of the access road to the Romaine complex dam site (trail outside the FCMQ networks)
    Footbridge over the Romaine River
    Located more or less 12 km west of Havre-St-Pierre, along route 138, two footbridges were necessary to cross the river due to their width as well as the size of the Romaine River.
    The Romaine Ouest footbridge is 55 m.l. long. and with a capacity of 10 T.M.
    The Romaine Est footbridge is one of the largest cable and suspension snowmobile footbridges of its kind (suspension bridge) in the world, according to our research. With a capacity of 10 t.m., it allows a resurfacer and its equipment to circulate. It has a length of 167 m.l. or 550’.
     
    P.S. For snowmobilers wishing to visit the North Shore and the Lower North Shore in the years to come, check if the trails will really be maintained by local clubs
    http://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0530.thumb.png.0615aa9d6d7f1a17399e6cc5902454be.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0531.thumb.png.20c8c822a4867a6d15813024ae5c572e.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0532.thumb.png.51d52b4f582643fd504d1e06731dd9f0.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0533.thumb.png.c9e0345d40f6ba5227885aaa19aab808.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0534.thumb.png.8c2530e62878b45add1db2852045f92d.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0535.thumb.png.dbdb08efe747bf21f4acb3db358a58b1.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0536.thumb.png.a7e9967ef4c6e1254ed896d75de45363.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0538.thumb.png.220e256ed033c8e14f81b1cb834477c4.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0539.thumb.png.10bff0a872943e996e4a8a5135409eca.png
  2. Thanks
    Trailblazer got a reaction from willb in Trail 3 complete   
    With the news of the Pessimite agreement and now the completion of several bridges on the North Shore Sept Isles, Havre St. Pierre and Baie Johan Beetz is now at our grasp.
    Below is the translation of the arcticle
    🎉 NEW ACHIEVEMENTS 🎉
    In the heart of Minganie, one of the largest snowmobile footbridge construction projects in the country is ending, namely the construction of 5 footbridges, 4 of which will serve the FCMQ trail. For almost 2 years, winter and summer, our team has been building footbridges on the Tortue, Aisley, Romaine rivers as well as Lac Cormier.
    We would first like to thank the SEIE, Les Constructions Mackenzie as well as the Innu Council of Ekuanitshit of Longue-Pointe-de-Mingan for their trust in our organization. Thank you also to all our subcontractors who participated directly or indirectly in the realization of these projects. Without forgetting, a huge thank you to all our valuable employees who brought these major projects to fruition! 💪
    Footbridge over the Tortue River
    23 ml long. and with a capacity of 20 t.m, this footbridge should allow the resumption of maintenance of the trail east of Sept-Îles which had been ungroomed for several years due to this missing bridge towards Havre-St-Pierre.
    Cormier Lake Footbridge
    235' long and with a capacity of 10 t.m, this footbridge is located above the Romaine 1 reservoir at km 19 of the access road to the Romaine complex dam site (trail outside the FCMQ networks)
    Footbridge over the Romaine River
    Located more or less 12 km west of Havre-St-Pierre, along route 138, two footbridges were necessary to cross the river due to their width as well as the size of the Romaine River.
    The Romaine Ouest footbridge is 55 m.l. long. and with a capacity of 10 T.M.
    The Romaine Est footbridge is one of the largest cable and suspension snowmobile footbridges of its kind (suspension bridge) in the world, according to our research. With a capacity of 10 t.m., it allows a resurfacer and its equipment to circulate. It has a length of 167 m.l. or 550’.
     
    P.S. For snowmobilers wishing to visit the North Shore and the Lower North Shore in the years to come, check if the trails will really be maintained by local clubs
    http://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0530.thumb.png.0615aa9d6d7f1a17399e6cc5902454be.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0531.thumb.png.20c8c822a4867a6d15813024ae5c572e.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0532.thumb.png.51d52b4f582643fd504d1e06731dd9f0.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0533.thumb.png.c9e0345d40f6ba5227885aaa19aab808.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0534.thumb.png.8c2530e62878b45add1db2852045f92d.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0535.thumb.png.dbdb08efe747bf21f4acb3db358a58b1.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0536.thumb.png.a7e9967ef4c6e1254ed896d75de45363.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0538.thumb.png.220e256ed033c8e14f81b1cb834477c4.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0539.thumb.png.10bff0a872943e996e4a8a5135409eca.png
  3. Like
    Trailblazer got a reaction from Florida Snowman in The New Sled Thread   
    Here’s my babies
    http://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0520.thumb.png.7a248ae63a62b4b344e0adae0bddc0b1.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0521.thumb.png.56897421d34fa25ba334180b39e5cdea.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0522.thumb.png.6e5ce47ee59ddcf2bfd5d11740b68eb8.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0523.thumb.png.2c76a3f4d2ac56c145cb003aca00e496.png
  4. Like
    Trailblazer got a reaction from P Hardy in Trail 3 complete   
    With the news of the Pessimite agreement and now the completion of several bridges on the North Shore Sept Isles, Havre St. Pierre and Baie Johan Beetz is now at our grasp.
    Below is the translation of the arcticle
    🎉 NEW ACHIEVEMENTS 🎉
    In the heart of Minganie, one of the largest snowmobile footbridge construction projects in the country is ending, namely the construction of 5 footbridges, 4 of which will serve the FCMQ trail. For almost 2 years, winter and summer, our team has been building footbridges on the Tortue, Aisley, Romaine rivers as well as Lac Cormier.
    We would first like to thank the SEIE, Les Constructions Mackenzie as well as the Innu Council of Ekuanitshit of Longue-Pointe-de-Mingan for their trust in our organization. Thank you also to all our subcontractors who participated directly or indirectly in the realization of these projects. Without forgetting, a huge thank you to all our valuable employees who brought these major projects to fruition! 💪
    Footbridge over the Tortue River
    23 ml long. and with a capacity of 20 t.m, this footbridge should allow the resumption of maintenance of the trail east of Sept-Îles which had been ungroomed for several years due to this missing bridge towards Havre-St-Pierre.
    Cormier Lake Footbridge
    235' long and with a capacity of 10 t.m, this footbridge is located above the Romaine 1 reservoir at km 19 of the access road to the Romaine complex dam site (trail outside the FCMQ networks)
    Footbridge over the Romaine River
    Located more or less 12 km west of Havre-St-Pierre, along route 138, two footbridges were necessary to cross the river due to their width as well as the size of the Romaine River.
    The Romaine Ouest footbridge is 55 m.l. long. and with a capacity of 10 T.M.
    The Romaine Est footbridge is one of the largest cable and suspension snowmobile footbridges of its kind (suspension bridge) in the world, according to our research. With a capacity of 10 t.m., it allows a resurfacer and its equipment to circulate. It has a length of 167 m.l. or 550’.
     
    P.S. For snowmobilers wishing to visit the North Shore and the Lower North Shore in the years to come, check if the trails will really be maintained by local clubs
    http://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0530.thumb.png.0615aa9d6d7f1a17399e6cc5902454be.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0531.thumb.png.20c8c822a4867a6d15813024ae5c572e.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0532.thumb.png.51d52b4f582643fd504d1e06731dd9f0.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0533.thumb.png.c9e0345d40f6ba5227885aaa19aab808.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0534.thumb.png.8c2530e62878b45add1db2852045f92d.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0535.thumb.png.dbdb08efe747bf21f4acb3db358a58b1.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0536.thumb.png.a7e9967ef4c6e1254ed896d75de45363.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0538.thumb.png.220e256ed033c8e14f81b1cb834477c4.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0539.thumb.png.10bff0a872943e996e4a8a5135409eca.png
  5. Like
    Trailblazer got a reaction from MrGutz in Trail 3 complete   
    With the news of the Pessimite agreement and now the completion of several bridges on the North Shore Sept Isles, Havre St. Pierre and Baie Johan Beetz is now at our grasp.
    Below is the translation of the arcticle
    🎉 NEW ACHIEVEMENTS 🎉
    In the heart of Minganie, one of the largest snowmobile footbridge construction projects in the country is ending, namely the construction of 5 footbridges, 4 of which will serve the FCMQ trail. For almost 2 years, winter and summer, our team has been building footbridges on the Tortue, Aisley, Romaine rivers as well as Lac Cormier.
    We would first like to thank the SEIE, Les Constructions Mackenzie as well as the Innu Council of Ekuanitshit of Longue-Pointe-de-Mingan for their trust in our organization. Thank you also to all our subcontractors who participated directly or indirectly in the realization of these projects. Without forgetting, a huge thank you to all our valuable employees who brought these major projects to fruition! 💪
    Footbridge over the Tortue River
    23 ml long. and with a capacity of 20 t.m, this footbridge should allow the resumption of maintenance of the trail east of Sept-Îles which had been ungroomed for several years due to this missing bridge towards Havre-St-Pierre.
    Cormier Lake Footbridge
    235' long and with a capacity of 10 t.m, this footbridge is located above the Romaine 1 reservoir at km 19 of the access road to the Romaine complex dam site (trail outside the FCMQ networks)
    Footbridge over the Romaine River
    Located more or less 12 km west of Havre-St-Pierre, along route 138, two footbridges were necessary to cross the river due to their width as well as the size of the Romaine River.
    The Romaine Ouest footbridge is 55 m.l. long. and with a capacity of 10 T.M.
    The Romaine Est footbridge is one of the largest cable and suspension snowmobile footbridges of its kind (suspension bridge) in the world, according to our research. With a capacity of 10 t.m., it allows a resurfacer and its equipment to circulate. It has a length of 167 m.l. or 550’.
     
    P.S. For snowmobilers wishing to visit the North Shore and the Lower North Shore in the years to come, check if the trails will really be maintained by local clubs
    http://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0530.thumb.png.0615aa9d6d7f1a17399e6cc5902454be.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0531.thumb.png.20c8c822a4867a6d15813024ae5c572e.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0532.thumb.png.51d52b4f582643fd504d1e06731dd9f0.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0533.thumb.png.c9e0345d40f6ba5227885aaa19aab808.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0534.thumb.png.8c2530e62878b45add1db2852045f92d.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0535.thumb.png.dbdb08efe747bf21f4acb3db358a58b1.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0536.thumb.png.a7e9967ef4c6e1254ed896d75de45363.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0538.thumb.png.220e256ed033c8e14f81b1cb834477c4.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0539.thumb.png.10bff0a872943e996e4a8a5135409eca.png
  6. Like
    Trailblazer got a reaction from markusvt in The New Sled Thread   
    Around home I ride with guys that have Thunder Cats and Sidewinders and they are very surprised how well the Extreme keeps up.
    The handling part all has to do with how you set it up.
  7. Thanks
    Trailblazer got a reaction from mccaffrey in Trail 3 complete   
    With the news of the Pessimite agreement and now the completion of several bridges on the North Shore Sept Isles, Havre St. Pierre and Baie Johan Beetz is now at our grasp.
    Below is the translation of the arcticle
    🎉 NEW ACHIEVEMENTS 🎉
    In the heart of Minganie, one of the largest snowmobile footbridge construction projects in the country is ending, namely the construction of 5 footbridges, 4 of which will serve the FCMQ trail. For almost 2 years, winter and summer, our team has been building footbridges on the Tortue, Aisley, Romaine rivers as well as Lac Cormier.
    We would first like to thank the SEIE, Les Constructions Mackenzie as well as the Innu Council of Ekuanitshit of Longue-Pointe-de-Mingan for their trust in our organization. Thank you also to all our subcontractors who participated directly or indirectly in the realization of these projects. Without forgetting, a huge thank you to all our valuable employees who brought these major projects to fruition! 💪
    Footbridge over the Tortue River
    23 ml long. and with a capacity of 20 t.m, this footbridge should allow the resumption of maintenance of the trail east of Sept-Îles which had been ungroomed for several years due to this missing bridge towards Havre-St-Pierre.
    Cormier Lake Footbridge
    235' long and with a capacity of 10 t.m, this footbridge is located above the Romaine 1 reservoir at km 19 of the access road to the Romaine complex dam site (trail outside the FCMQ networks)
    Footbridge over the Romaine River
    Located more or less 12 km west of Havre-St-Pierre, along route 138, two footbridges were necessary to cross the river due to their width as well as the size of the Romaine River.
    The Romaine Ouest footbridge is 55 m.l. long. and with a capacity of 10 T.M.
    The Romaine Est footbridge is one of the largest cable and suspension snowmobile footbridges of its kind (suspension bridge) in the world, according to our research. With a capacity of 10 t.m., it allows a resurfacer and its equipment to circulate. It has a length of 167 m.l. or 550’.
     
    P.S. For snowmobilers wishing to visit the North Shore and the Lower North Shore in the years to come, check if the trails will really be maintained by local clubs
    http://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0530.thumb.png.0615aa9d6d7f1a17399e6cc5902454be.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0531.thumb.png.20c8c822a4867a6d15813024ae5c572e.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0532.thumb.png.51d52b4f582643fd504d1e06731dd9f0.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0533.thumb.png.c9e0345d40f6ba5227885aaa19aab808.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0534.thumb.png.8c2530e62878b45add1db2852045f92d.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0535.thumb.png.dbdb08efe747bf21f4acb3db358a58b1.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0536.thumb.png.a7e9967ef4c6e1254ed896d75de45363.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0538.thumb.png.220e256ed033c8e14f81b1cb834477c4.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0539.thumb.png.10bff0a872943e996e4a8a5135409eca.png
  8. Like
    Trailblazer got a reaction from GSX800 in Trail 3 complete   
    With the news of the Pessimite agreement and now the completion of several bridges on the North Shore Sept Isles, Havre St. Pierre and Baie Johan Beetz is now at our grasp.
    Below is the translation of the arcticle
    🎉 NEW ACHIEVEMENTS 🎉
    In the heart of Minganie, one of the largest snowmobile footbridge construction projects in the country is ending, namely the construction of 5 footbridges, 4 of which will serve the FCMQ trail. For almost 2 years, winter and summer, our team has been building footbridges on the Tortue, Aisley, Romaine rivers as well as Lac Cormier.
    We would first like to thank the SEIE, Les Constructions Mackenzie as well as the Innu Council of Ekuanitshit of Longue-Pointe-de-Mingan for their trust in our organization. Thank you also to all our subcontractors who participated directly or indirectly in the realization of these projects. Without forgetting, a huge thank you to all our valuable employees who brought these major projects to fruition! 💪
    Footbridge over the Tortue River
    23 ml long. and with a capacity of 20 t.m, this footbridge should allow the resumption of maintenance of the trail east of Sept-Îles which had been ungroomed for several years due to this missing bridge towards Havre-St-Pierre.
    Cormier Lake Footbridge
    235' long and with a capacity of 10 t.m, this footbridge is located above the Romaine 1 reservoir at km 19 of the access road to the Romaine complex dam site (trail outside the FCMQ networks)
    Footbridge over the Romaine River
    Located more or less 12 km west of Havre-St-Pierre, along route 138, two footbridges were necessary to cross the river due to their width as well as the size of the Romaine River.
    The Romaine Ouest footbridge is 55 m.l. long. and with a capacity of 10 T.M.
    The Romaine Est footbridge is one of the largest cable and suspension snowmobile footbridges of its kind (suspension bridge) in the world, according to our research. With a capacity of 10 t.m., it allows a resurfacer and its equipment to circulate. It has a length of 167 m.l. or 550’.
     
    P.S. For snowmobilers wishing to visit the North Shore and the Lower North Shore in the years to come, check if the trails will really be maintained by local clubs
    http://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0530.thumb.png.0615aa9d6d7f1a17399e6cc5902454be.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0531.thumb.png.20c8c822a4867a6d15813024ae5c572e.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0532.thumb.png.51d52b4f582643fd504d1e06731dd9f0.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0533.thumb.png.c9e0345d40f6ba5227885aaa19aab808.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0534.thumb.png.8c2530e62878b45add1db2852045f92d.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0535.thumb.png.dbdb08efe747bf21f4acb3db358a58b1.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0536.thumb.png.a7e9967ef4c6e1254ed896d75de45363.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0538.thumb.png.220e256ed033c8e14f81b1cb834477c4.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0539.thumb.png.10bff0a872943e996e4a8a5135409eca.png
  9. Like
    Trailblazer got a reaction from wng-2 in Trail 3 complete   
    With the news of the Pessimite agreement and now the completion of several bridges on the North Shore Sept Isles, Havre St. Pierre and Baie Johan Beetz is now at our grasp.
    Below is the translation of the arcticle
    🎉 NEW ACHIEVEMENTS 🎉
    In the heart of Minganie, one of the largest snowmobile footbridge construction projects in the country is ending, namely the construction of 5 footbridges, 4 of which will serve the FCMQ trail. For almost 2 years, winter and summer, our team has been building footbridges on the Tortue, Aisley, Romaine rivers as well as Lac Cormier.
    We would first like to thank the SEIE, Les Constructions Mackenzie as well as the Innu Council of Ekuanitshit of Longue-Pointe-de-Mingan for their trust in our organization. Thank you also to all our subcontractors who participated directly or indirectly in the realization of these projects. Without forgetting, a huge thank you to all our valuable employees who brought these major projects to fruition! 💪
    Footbridge over the Tortue River
    23 ml long. and with a capacity of 20 t.m, this footbridge should allow the resumption of maintenance of the trail east of Sept-Îles which had been ungroomed for several years due to this missing bridge towards Havre-St-Pierre.
    Cormier Lake Footbridge
    235' long and with a capacity of 10 t.m, this footbridge is located above the Romaine 1 reservoir at km 19 of the access road to the Romaine complex dam site (trail outside the FCMQ networks)
    Footbridge over the Romaine River
    Located more or less 12 km west of Havre-St-Pierre, along route 138, two footbridges were necessary to cross the river due to their width as well as the size of the Romaine River.
    The Romaine Ouest footbridge is 55 m.l. long. and with a capacity of 10 T.M.
    The Romaine Est footbridge is one of the largest cable and suspension snowmobile footbridges of its kind (suspension bridge) in the world, according to our research. With a capacity of 10 t.m., it allows a resurfacer and its equipment to circulate. It has a length of 167 m.l. or 550’.
     
    P.S. For snowmobilers wishing to visit the North Shore and the Lower North Shore in the years to come, check if the trails will really be maintained by local clubs
    http://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0530.thumb.png.0615aa9d6d7f1a17399e6cc5902454be.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0531.thumb.png.20c8c822a4867a6d15813024ae5c572e.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0532.thumb.png.51d52b4f582643fd504d1e06731dd9f0.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0533.thumb.png.c9e0345d40f6ba5227885aaa19aab808.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0534.thumb.png.8c2530e62878b45add1db2852045f92d.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0535.thumb.png.dbdb08efe747bf21f4acb3db358a58b1.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0536.thumb.png.a7e9967ef4c6e1254ed896d75de45363.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0538.thumb.png.220e256ed033c8e14f81b1cb834477c4.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0539.thumb.png.10bff0a872943e996e4a8a5135409eca.png
  10. Like
    Trailblazer got a reaction from zeusand in Trail 3 complete   
    With the news of the Pessimite agreement and now the completion of several bridges on the North Shore Sept Isles, Havre St. Pierre and Baie Johan Beetz is now at our grasp.
    Below is the translation of the arcticle
    🎉 NEW ACHIEVEMENTS 🎉
    In the heart of Minganie, one of the largest snowmobile footbridge construction projects in the country is ending, namely the construction of 5 footbridges, 4 of which will serve the FCMQ trail. For almost 2 years, winter and summer, our team has been building footbridges on the Tortue, Aisley, Romaine rivers as well as Lac Cormier.
    We would first like to thank the SEIE, Les Constructions Mackenzie as well as the Innu Council of Ekuanitshit of Longue-Pointe-de-Mingan for their trust in our organization. Thank you also to all our subcontractors who participated directly or indirectly in the realization of these projects. Without forgetting, a huge thank you to all our valuable employees who brought these major projects to fruition! 💪
    Footbridge over the Tortue River
    23 ml long. and with a capacity of 20 t.m, this footbridge should allow the resumption of maintenance of the trail east of Sept-Îles which had been ungroomed for several years due to this missing bridge towards Havre-St-Pierre.
    Cormier Lake Footbridge
    235' long and with a capacity of 10 t.m, this footbridge is located above the Romaine 1 reservoir at km 19 of the access road to the Romaine complex dam site (trail outside the FCMQ networks)
    Footbridge over the Romaine River
    Located more or less 12 km west of Havre-St-Pierre, along route 138, two footbridges were necessary to cross the river due to their width as well as the size of the Romaine River.
    The Romaine Ouest footbridge is 55 m.l. long. and with a capacity of 10 T.M.
    The Romaine Est footbridge is one of the largest cable and suspension snowmobile footbridges of its kind (suspension bridge) in the world, according to our research. With a capacity of 10 t.m., it allows a resurfacer and its equipment to circulate. It has a length of 167 m.l. or 550’.
     
    P.S. For snowmobilers wishing to visit the North Shore and the Lower North Shore in the years to come, check if the trails will really be maintained by local clubs
    http://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0530.thumb.png.0615aa9d6d7f1a17399e6cc5902454be.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0531.thumb.png.20c8c822a4867a6d15813024ae5c572e.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0532.thumb.png.51d52b4f582643fd504d1e06731dd9f0.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0533.thumb.png.c9e0345d40f6ba5227885aaa19aab808.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0534.thumb.png.8c2530e62878b45add1db2852045f92d.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0535.thumb.png.dbdb08efe747bf21f4acb3db358a58b1.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0536.thumb.png.a7e9967ef4c6e1254ed896d75de45363.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0538.thumb.png.220e256ed033c8e14f81b1cb834477c4.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0539.thumb.png.10bff0a872943e996e4a8a5135409eca.png
  11. Like
    Trailblazer got a reaction from smclelan in The New Sled Thread   
    Around home I ride with guys that have Thunder Cats and Sidewinders and they are very surprised how well the Extreme keeps up.
    The handling part all has to do with how you set it up.
  12. Like
    Trailblazer reacted to markusvt in Rain coming   
    It's been snow on warm ground. Trails always last longer if you can have some warm, rain, soak in and refreeze.  That how I figure.  Now if it all melts everywhere back to ground zero, that would be a bummer.  I already put in close to 1000 miles this year up there and it was deep snow all the way down to unfrozen dirt, trails will last longer with a base.
  13. Like
    Trailblazer reacted to markusvt in Rain coming   
    For long term good trails, some of this will be good.
  14. Like
    Trailblazer got a reaction from mccaffrey in The New Sled Thread   
    Here’s my babies
    http://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0520.thumb.png.7a248ae63a62b4b344e0adae0bddc0b1.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0521.thumb.png.56897421d34fa25ba334180b39e5cdea.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0522.thumb.png.6e5ce47ee59ddcf2bfd5d11740b68eb8.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0523.thumb.png.2c76a3f4d2ac56c145cb003aca00e496.png
  15. Like
    Trailblazer got a reaction from MrGutz in The New Sled Thread   
    Here’s my babies
    http://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0520.thumb.png.7a248ae63a62b4b344e0adae0bddc0b1.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0521.thumb.png.56897421d34fa25ba334180b39e5cdea.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0522.thumb.png.6e5ce47ee59ddcf2bfd5d11740b68eb8.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0523.thumb.png.2c76a3f4d2ac56c145cb003aca00e496.png
  16. Like
    Trailblazer got a reaction from dooright in The New Sled Thread   
    Here’s my babies
    http://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0520.thumb.png.7a248ae63a62b4b344e0adae0bddc0b1.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0521.thumb.png.56897421d34fa25ba334180b39e5cdea.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0522.thumb.png.6e5ce47ee59ddcf2bfd5d11740b68eb8.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0523.thumb.png.2c76a3f4d2ac56c145cb003aca00e496.png
  17. Like
    Trailblazer got a reaction from markusvt in The New Sled Thread   
    Here’s my babies
    http://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0520.thumb.png.7a248ae63a62b4b344e0adae0bddc0b1.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0521.thumb.png.56897421d34fa25ba334180b39e5cdea.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0522.thumb.png.6e5ce47ee59ddcf2bfd5d11740b68eb8.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0523.thumb.png.2c76a3f4d2ac56c145cb003aca00e496.png
  18. Like
    Trailblazer got a reaction from mikerider in The New Sled Thread   
    Here’s my babies
    http://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0520.thumb.png.7a248ae63a62b4b344e0adae0bddc0b1.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0521.thumb.png.56897421d34fa25ba334180b39e5cdea.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0522.thumb.png.6e5ce47ee59ddcf2bfd5d11740b68eb8.pnghttp://quebecrider.com/forums/uploads/monthly_2023_12/IMG_0523.thumb.png.2c76a3f4d2ac56c145cb003aca00e496.png
  19. Like
    Trailblazer got a reaction from smclelan in Cote Nord Trail 3 Pessamit Shuttle   
    Me too
  20. Like
    Trailblazer got a reaction from dooright in Cote Nord Trail 3 Pessamit Shuttle   
    Me too
  21. Like
    Trailblazer got a reaction from markusvt in Cote Nord Trail 3 Pessamit Shuttle   
    Me too
  22. Like
    Trailblazer reacted to markusvt in Cote Nord Trail 3 Pessamit Shuttle   
    I read agreement reached yesterday for the 23/24 season.
  23. Like
    Trailblazer got a reaction from Florida Snowman in The New Sled Thread   
    You at the Rack Shack Terry?
    Now that you have all the time in the world we have to get together and do a ride this season.
  24. Like
    Trailblazer reacted to neksledr in The New Sled Thread   
    Just say the word JG, I'm ready!
  25. Like
    Trailblazer got a reaction from smclelan in The New Sled Thread   
    You at the Rack Shack Terry?
    Now that you have all the time in the world we have to get together and do a ride this season.
×
×
  • Create New...