Finally, we can unveil the new permanent route to circumvent the legendary Bell Cabin.This will allow us even more autonomy this winter versus the transport of wood which had delayed the start of last season by leaving us several rocks as a gift.

This new route, 10 kilometers long, required the addition of 15 culverts and was completed in 24 days by Excavation Gaston Clavet and its day laborer Claude Perreault.

This newly built trail will give you a spectacular view and will enhance your journey. The new route of the trail will be officially on IMotoneige as soon as we have the chance to go there by snowmobile in order to take the GPS reading and then send it to the federation (FCMQ)

. On the first photo you can see the old route and on the second, the new one.

Special thanks to the Séminaire de Québec, to Excavation Gaston Clavet and to Claude Perreault, our president, for the time spent in the field.

 

8ED6184B-2873-4DB5-A8AE-3D7CD5F456AE.jpeg

10FA6392-EC80-469D-9874-21CAAE437356.jpeg

Link to comment
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Restore formatting

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

 Share

×
×
  • Create New...